Country Aire Estates Reconstruction Phase 1

Default Rowlett Image 2

Country Aire Estates Reconstruction Phase 1 involves the reconstruction of Salzburg Drive between Chiesa Road and Acapulco Drive.

  • Construction Work Start Date:  January 8, 2024.
  •   Funding: 2021 Go Bond Fund.
  •  Project Scope: Reconstruction of the existing 27-foot-wide street to a 31-foot-wide concrete roadway, installation of a 5-foot-wide sidewalk on both sides of the street,
  •   installation of water and wastewater systems, sidewalks, and LED streetlights.
  •  Contractor: Quality Excavation, LLC
  •  Duration: Anticipated construction time is 150 calendar days, with an expected completion date of June 2024.

Subdivision map showing traffic control plan